MANILA, Philippines — The Metropolitan Manila Development Authority (MMDA) has proposed the construction of rainwater impounding facilities inside Camp Aguinaldo to ease recurring flooding along EDSA, with the proposed design released on Wednesday.

The plan calls for detention ponds that will temporarily store excess rainwater during downpours and gradually release it into the EDSA drainage system leading to Makiling Creek.
According to the proposal, the project will be implemented in three phases covering 182 hectares: a golf course near Gate 2, another near Gates 3 and 4, and an open space near Gate 6.
For the first phase near Gate 2, the detention pond has a 361-meter perimeter, a 4,650-square-meter area, an 8-meter depth, and a 37,200-cubic-meter capacity, designed for a 25-year return period (15.6 mm/hr over 24 hours) and exceeding the needed 36,945 cubic meters.
MMDA’s schematic shows that under normal weather, water bypasses the pond and traverses the lagoon to EDSA; during heavy rains, floodgates divert flows into the pond; after rains, pumps discharge stored water slowly to EDSA toward Makiling Creek.
The scope of work covers the impounding area, an operations and power house, drainage and electromechanical works, and landscaping and golf course restoration, with a treatment facility under consideration.
MMDA unveils plan to build rainwater impounding facilities in Camp Aguinaldo, This news data comes from:http://www.erlvyiwan.com
Officials said operations and maintenance arrangements and a memorandum of agreement were being discussed..
- Van Gogh Museum 'could close' without more help from Dutch govt
- US appeals court blocks Trump's use of wartime law for deportations
- IBP to form good governance panel
- Dial 911: New nationwide emergency hotline to go live on Sept. 11
- Bolsonaro verdict looms as Brazil coup trial closes
- Putin threatens to target Western troops in Ukraine
- SSS rolls out historic pension reform program
- Customs recovers 10 more Discaya luxury cars
- MMDA proposes rainwater facilities in Camp Aguinaldo to mitigate EDSA flooding
- House tackles P881B public works budget amid flood control anomalies